We appointed Dyer and Butler to carry out the refurbishment.
Work to Cleveland Bridge started on 4 May 2021, with the first stage being to construct the site compound and erect scaffolding, using off-peak temporary signals to make space for the work.
The bridge will re-open to two-way traffic in early October 2022.
Date | Project stage | Traffic restriction |
---|---|---|
4 May 2021 | Project start | Traffic signal control |
28 June to October 2021 | Main structural repair | Closed to all traffic |
25 October 2021 to early October 2022 | Additional structural works | Traffic signal control, light traffic only |
Early October 2022 | Completion works and demobilisation | Traffic signal control, light traffic only |